DONE 2026-08-18 — ~/Business/clients/chop-n-drop/seo-audit/2026-08-18/AUDIT.md. Rankings rechecked 2026-08-25 (../2026-08-25/RECHECK.md): positions flat, but PBN link acquisition is ONGOING (spam-anchor referring …
STOPPED HERE — awaiting Jack/client approval
in progress — awaiting sign-off. approved by: <pending>
DONE, gate approved by Jack 2026-08-18
OUTSTANDING — not yet run
OUTSTANDING — not yet run
every inner page designed to the approved direction
approved design rebuilt as a componentised Figma file
the design reference signed off — Figma file, Cloudflare build or CMS staging, whichever this project used
built in the target CMS (Beaver Builder / Elementor / Webflow) via the bridge
raw-HTML sections converted to native, client-editable CMS modules
launch checklist: redirects, forms, tracking, 404s, performance
DNS / hosting flipped — the new site goes live
seo-preservation VERIFY: re-crawl vs baseline, every old URL 301s, rankings re-checked. Done = confirmed live
2–4 week watch: GSC coverage, 404s, rankings vs baseline — after this the website is complete and it's maintenance from here
Not applicable to this project: BASELINE